BuiltPaper

How to Write a Change Order

Updated June 2026·6 min read

The short answer: A change order needs a clear description of the changed scope, the cost adjustment broken out, the schedule impact, the new contract total, a reference to the original contract, and a signature line for each side. Write it, price it, and get it signed before you do the work. A verbal yes does not get you paid.

A change order is the written amendment that adjusts your contract when the job changes. If you need the basics first, see what is a change order. This guide is about writing one that actually gets you signed and paid.

What every change order needs

A change order is a mini-contract. It has to stand on its own and tie back to the original deal. Leave out a piece and you give the other side room to argue later.

Here are the parts every change order needs:

PieceWhat it does
Reference to the original contractTies the change to the signed job (contract number or date)
Description of the changed scopeStates exactly what is being added, removed, or altered
Cost adjustmentThe dollar change, broken out so it is not a mystery number
Schedule impactHow many days this adds to the completion date
New contract totalThe original price plus this change, stated as one number
Signature linesA dated line for you and a dated line for the owner or GC

The cost adjustment is where most disputes start. Break it out. If quartz adds material and labor, show both. A single lump sum with no detail invites pushback.

The change order process, step by step

Run the same process every time. The order matters, because the goal is a signature before you lift a tool.

  1. Spot the change. The owner asks for something outside the original scope, or a site condition forces it. The moment the work no longer matches the contract, it is a change.
  2. Document the scope and price before you do the work. Write the description, price the cost adjustment, and figure the schedule hit. Do this first, not after.
  3. Submit it for written approval. Hand it over as its own document, not a line buried in an email or a text. Make it easy to read and easy to sign.
  4. Get it signed. Both sides date and sign. Now you have an amended contract and a price you can collect.
  5. Then do the work. Once it is signed, build it. Not before.

The whole point is step 4 before step 5. Get the signature first, and the change order does its job. Do the work first and you are negotiating from behind.

A worked example

Say you are mid-way through a kitchen remodel. The contract specs laminate counters. The owner walks the job and asks to upgrade to quartz.

That is a change. Here is how you write it.

ItemDetail
ReferencesContract dated March 3, 2026, kitchen remodel
Scope changeUpgrade kitchen counters from laminate to quartz, 40 sq ft
MaterialQuartz slab and edge work: $2,800
LaborRemoval of laminate, template, and install: $1,400
Cost adjustment+$4,200
Schedule impact+5 business days (slab fabrication lead time)
New contract total$38,000 original + $4,200 = $42,200

You write that up, hand it to the owner, and they sign and date it. Now the quartz is locked in at $4,200 and the completion date moves out five days, in writing, before you order the slab. If they balk at the price or the delay, you find out now, not after the laminate is in the dumpster.

Common mistakes that cost you

These are the ones that turn a simple change into an unpaid argument.

Get it signed before the work whenever you can. A verbal yes feels like agreement, but it does not hold up when the bill arrives. The signature is what gets you paid.

This is general information, not legal advice. Your contract has its own change-order clause that sets how changes must be approved, so follow that clause and confirm anything you are unsure of.

Key takeaways
  • Every change order needs scope, cost, schedule impact, the new total, a contract reference, and two signatures.
  • Run the same process every time: spot it, document and price it, get it signed, then build it.
  • Get the signature before the work. A verbal yes does not get you paid.
  • Break out the cost and name the scope. Vague descriptions and unsigned forms cause disputes.
Write a change order in 2 minutes
Fill in the scope, price, and schedule change, sign on screen, and download a branded PDF.
Open the generator →

Frequently asked questions

What should a change order include?+

Every change order needs six pieces: a reference to the original contract, a clear description of the changed scope, the cost adjustment broken out, the schedule impact in days, the new contract total, and a dated signature line for each side.

Do I need a change order signed before starting work?+

Yes, whenever you can. Get it signed before you do the work, because a signed change order is an amended contract you can collect on. A verbal yes feels like agreement but does not hold up when the bill arrives.

What is a change order example?+

Say a kitchen remodel specs laminate counters and the owner asks for quartz. You write a change order that references the original contract, describes the quartz upgrade, breaks out material and labor, adds days for fabrication, and states the new contract total. Both sides sign before you order the slab.

How do I price a change order?+

Break the cost out so it is not a mystery number. Show material and labor separately, add any equipment or markup your contract allows, and state the total dollar change as a plus or minus. Price it before you do the work, not after.

Can a change order be verbal?+

Treat it as no. A verbal agreement does not amend your contract and does not get you paid when the customer disputes the cost. Put it in writing, get both sides to sign and date it, then build the work.

Related guides

Informational and educational only. Not legal advice and not a law firm. Confirm the rules for your state, role, and project, or consult a construction attorney, before you rely on this.